Automated maintenance management

With the aim of effectively prioritising maintenance expenditure, and carrying it out efficiently, Sutherland Shire in Sydney’s south has developed an activity based costing model for its civil maintenance operation.

Under the system, known as the Maintenance Management and Job Costing system, work teams using palm top computers log details of works required. This is then automatically uploaded to Council’s main computer system.

At this point, pre ordained criteria sort the jobs into priority order. These include the nature and severity of the defect. It also takes into account the location and exposure of the asset and the risk it represents.

When the work is carried out Maintenance Foremen use the palmtops to log the labour, hours, plant and materials used. This data is used to generate an ‘invoice’ which is charged against the appropriate funding budget account. Likewise, corresponding income is automatically credited to the work team’s account.

All work team costs including labour, plant, materials replacement, tools and sundry items, are charged to an expenditure account established for each team.

The value of output is determined by applying the ‘All Team Average Job Costs’ to the jobs completed by individual teams.

Comparison of this data allows identification of best practice among the teams with a view to improving overall performance.

Above all, the work must be performed with consideration of Council requirements in terms of workplace health and safety, conformity to specifications and applicable environmental controls.

Comparison of each team’s performance allows for performance bonuses based on Work Team Profitability assessed on the basis of the data.

Manager Civil Works, Mario Sherrie, said the system has been enthusiastically supported by work team members since it was first developed in 1998.

He said it has increased the effectiveness of maintenance operations by facilitating the identification and prioritisation of necessary works.

In the future, the system is expected to accommodate the recording of implementing Traffic Control Plans. This will provide an audit trail in accordance with RTA recommendations.

It will also allow automatic updating of Council’s corporate Customer Request Management System and linkage of the system with Council’s GIS to accurately locate asset defects.

For further information contact Mario Sherrie, telephone (02) 9710 5724.

Digital Editions


  • Looking to the future

    Looking to the future

    Flinders Lane will be abuzz for two days this month with Townsville Youth Council – supported by Townsville City Council – set to deliver a…

More News

  • A golden celebration

    A golden celebration

    Cockburn Libraries will mark a major milestone in 2026 – 50 years of serving, supporting and connecting the community. Spearwood Library opened its doors on 23 March 1976 as one…

  • Local Governments vital for fuel supply

    Local Governments vital for fuel supply

    Fuel supply constraints and rising costs are putting councils and communities under increasing pressure across Australia, with implications for essential services and community infrastructure. The Australian Local Government Association is…

  • Nathan Daniell elected Mayor of Adelaide Hills Council

    Nathan Daniell elected Mayor of Adelaide Hills Council

    Adelaide Hills Council is pleased to advise that Nathan Daniell has formally been elected Mayor following confirmation of results from the supplementary election. Mr Daniell has served as a councillor…

  • Community mourns beloved former mayor

    Community mourns beloved former mayor

    The NSW local government sector is deeply saddened by the passing of former Lismore Mayor Jenny Dowell OAM, a widely respected and much-loved leader who dedicated her life to serving…

  • New-look reserve reopens

    New-look reserve reopens

    Toongabbie’s Sue Savage Reserve has reopened after a $4 million upgrade featuring a new skate park, BMX pump track, fitness equipment, an amenity building, park furniture, drainage upgrade, landscaping and…

  • Temora address housing shortage in tiny hamlet

    Temora address housing shortage in tiny hamlet

    Proposed Ariah Park Village Subdivision to Address Housing Shortage – Lots from $90-000 to $110,000 in the small picturesque hamlet. Temora Shire Council is investigating the delivery of a proposed…

  • Douglas Shire seeks renewal

    Douglas Shire seeks renewal

    Creative store opens in Mossman through empty spaces program. A new store and community art space has opened in Mossman thanks to a program designed to breathe new life into…

  • New youth and community centre for McLeay

    New youth and community centre for McLeay

    A new Youth and Community Centre planned for Macleay Island will service the needs of the growing community and will also be designed so it can support community recovery following…

  • Grants close soon

    Grants close soon

    Queensland councils have until 31 March to apply for Round two of the State Government’s Secure Communities Partnership Program, which offers up to $400,000 per project for CCTV, lighting and…

  • Sod turned on major upgrade at Paul Fitzsimons Oval

    Sod turned on major upgrade at Paul Fitzsimons Oval

    Work has officially begun on the redevelopment of Paul Fitzsimons Oval with Alice Springs Town Council and the Australian Government turning the first sod this morning. Mayor Asta Hill and…