Future directions in best practice

Following three years of planning and almost nine months of night work, the program to roll out Microsoft’s Windows 7 across the Fraser Coast Regional Council is winding up.

With the recognition that Windows XP had reached the end of its life, work has started on moving the entire system over to its replacement.
Principal Officer IT Infrastructure John Knott said, “The initial planning involved talking with Council’s software suppliers to work through any upgrades they would need to ensure their programs were compatible with Windows 7.

“We waited as long as possible to replace XP and Office 2003 to ensure that our financial, property and records systems would support Windows 7.”

The roll out, across 470 computers at five sites, involved replacing Windows XP and Office 2003 with Windows 7 and Office 2010.

“We spent several months earlier this year building a standard operating system and testing,” said John Knott.

“The original build was tested in IT and then rolled out to Records to make sure it was compatible with their systems. After a couple of revisions we moved to a small user trial involving Human Resources.”

From that point, a small group was selected from volunteers in each department to act as a pilot group who would test the upgrades against the programs they used daily.

“The idea was that they would test the operating system so we could debug,”

John said. “Those staff would then be familiar enough with the programs to become the ‘go to’ people in each section so they could help train their workmates.”

The roll out started with the Hervey Bay administration centre, moved on to the Maryborough administration centre, the Moreton Street depot in Maryborough, Parks in Hervey Bay and, finally, to the Hervey Bay depot.

“The Hervey Bay depot, with the engineering section, was saved until last because it was going to provide the most challenges,” John said. “Along the way we have had to make sure that the new system was compatible with more than 1500 different software packages that are in use across Council.”

The entire upgrade to Windows 7 was carried out internally. “We did not call in consultants or outsource. The upgrades were completed as staff went on holidays, took an RDO or in batches at night,” John commented.

“A team of two stayed back each night to upgrade between 15 and 20 computers. They would make sure there were no problems from their end before going home and then would visit each user the next morning to make sure everything was functioning and carry out any debugging. It has been a fairly smooth process but inevitably a few printers crashed and machines did not work.”

In recognition of his efforts and role in the smooth roll out of Windows 7, the IT staff member heading up the project, Roger Johnston, was awarded a High Achiever Award for August in Council’s Customer Services Awards.

Digital Editions


More News

  • Major repairs for levee

    Major repairs for levee

    Goondiwindi Regional Council has endorsed its largest-ever capital works project to repair and reinforce critical sections of the Goondiwindi levee, following significant erosion after recent floods. At this week’s Ordinary…

  • Stretching for a good cause

    Stretching for a good cause

    Ballarat residents stretched, smiled and snuggled their way through a unique Kitten Yoga event that combined relaxation with a heartwarming cause – helping kittens find their forever homes. Hosted by…

  • Murray Library upgrade open

    Murray Library upgrade open

    The Murray Library refurbishment is now complete, and the revitalised space is officially open to the community. The upgrade delivers a brighter, more accessible and flexible library that reflects the…

  • Lockyer announce Scott Greensill as CEO

    Lockyer announce Scott Greensill as CEO

    Lockyer Valley Regional Council has appointed Scott Greensill as its new Chief Executive Officer. Councillors formally approved the appointment of Mr Greensill at a Special Meeting of Council in February.…

  • Myers resigns for health reasons

    Myers resigns for health reasons

    Wollongong’s Councillor Tiana Myers has resigned, as a Ward Three Councillor for City Council due to health reasons. Cr Myers was elected to Council in 2024 with a focus on…

  • Acknowledging women’s role in councils

    Acknowledging women’s role in councils

    Council representatives from across the state gathered in Sydney today for Local Government NSW’s (LGNSW) International Women’s Day event. Mayor Darcy Byrne, President of LGNSW, said the event was an…

  • Kylie Davies beats strong field

    Kylie Davies beats strong field

    Flinders Shire Council is pleased to announce the appointment of Kylie Davies as its new Chief Executive Officer. Ms Davies will start in the role on 13 April following a…

  • Leaving on a high

    Leaving on a high

    Mount Alexander Shire Council’s Chief Executive Officer Darren Fuzzard will end his tenure at the council in July 2026, marking ten years of service to the organisation and community. Mr…

  • Safety first for transport corridor

    Safety first for transport corridor

    Traversing a major Townsville transit corridor spanning three suburbs will soon be safer for motorists, cyclists and pedestrians, with Townsville City Council commencing a $3.8 million upgrade of Hugh and…

  • Creating long-term employment pathways

    Creating long-term employment pathways

    The Shire of Carnarvon is creating long-term employment pathways and strengthening workforce capability through its participation in the Remote Jobs and Economic Development (RJED) Program, a national initiative designed to…