Home » Lismore four years on

Lismore four years on

Four years on: How Lismore is building back and setting a national benchmark.

When the 2022 flood inundated Lismore, it was not simply another extreme weather event. It became Australia’s most significant natural

disaster in recorded history, devastating homes, businesses and critical infrastructure across the city.

Four years on, the defining story is not just about restoration. It is about reform.

Lismore did not have the benefit of a precedent.

Unlike in Queensland, there were no established guidelines or templates for a disaster of this magnitude. That meant Council had to develop the

settings as the work rolled out. In doing so, Lismore has helped reshape how large-scale recovery programs are structured, governed and

delivered, setting a new national standard.

Since 2023, Council has been managing a $1 billion flood restoration portfolio spanning 338 projects, the largest capital works program ever

undertaken by a council in NSW and unprecedented nationally in a local government context.

The portfolio spans roads and bridges, landslip remediation, public buildings, and water and waste infrastructure. It is a complex program

typically associated with state agencies.

At the four-year milestone, 133 flood-restoration projects are complete, another 142 are in active delivery, 135 contracts have been executed,

and $145 million in works are underway. More than $200 million has flowed directly into local and regional businesses, supporting jobs and

economic recovery.

Administering a program of this scale required a fundamental reset of internal systems. Procurement frameworks were redesigned. Contract

management disciplines were strengthened. Risk oversight and reporting processes were recalibrated to align with the heightened scrutiny and obligations.

Importantly, these have not been temporary overlays.

The governance uplift required has been embedded into Council’s permanent operating model.

The result is award-winning practices and a regional council operating at a program management maturity level on par with major infrastructure

agencies.

Physical reconstruction has been equally deliberate.

Key community assets have been restored with resilience upgrades designed to better withstand future events. Lismore City Library, Lismore

Memorial Baths, the Lismore Municipal Building and the Lismore Regional Gallery are once again operational, not just reopened but

strengthened by design.

Technology has been a practical enabler of this resilience shift. Council completed a new 10-kilometre fibre optic network to support remote

monitoring and operation of critical wastewater pump systems, improving response times and safety during flood events.

Flood monitoring cameras also now provide real-time visual updates, reducing unnecessary travel into high-risk zones and helping the

community stay informed.

Four years on, the lesson from Lismore is simple: when disaster strikes, rebuilding is only part of the task. The greater opportunity is to rebuild

institutional capability that underpins it. Lismore has done both and is ready for the future.

Digital Editions


  • New paint technology at Alexandrina

    New paint technology at Alexandrina

    A paint trial is taking the heat out of Alexandrina’s council infrastructure. Alexandrina Council’s Alexandrina Wastewater division is trialing new paint technology to cool down…

More News

  • Together Butchulla Talk

    Together Butchulla Talk

    A new Indigenous book celebrating the Butchulla language and local animals was launched at Hervey Bay Library earlier this month with storytime, language, dance and art activities for families to…

  • New Logan arena

    New Logan arena

    An upgraded arena for equestrians has officially opened at Skerman Park in North Maclean. Logan City Council delivered the $928,000 project, which includes a weatherproof roof, to support members of…

  • Noosa mastering AI

    Noosa mastering AI

    Digital Hub is trying to help Noosa locals get the most out of AI. Mastering AI can make life easier in countless ways. From planning weekly meals with specific dietary…

  • Change in the weather

    Change in the weather

    AUSSIE FLOOD RESCUE It’s obvious to everybody that we are seeing weather changes. It appears to be more erratic and frequent than ever before. Local government bodies are plagued by…

  • Dandycon set to return

    Dandycon set to return

    Dandy Con, Greater Dandenong’s much loved comic and pop culture festival, returns on Saturday 11 April 2026 between 11am–4pm, bigger than ever. This free, all ages event fills Dandenong Library,…

  • A creative future for Kingston

    A creative future for Kingston

    The community has been invited to help shape Kingston’s creative and cultural future. Kingston residents are being invited to help finalise the city’s cultural roadmap, with the Draft Creative and…

  • Tweed residents gunking up wastewater

    Tweed residents gunking up wastewater

    Tweed Shire Council is urging residents to rethink what they flush down the toilet and pour down the drain, after revealing that crews remove around 156 tonnes of rubbish and…

  • In memory of Chris Quilkey

    In memory of Chris Quilkey

    It was with great sadness that we learned that former Blacktown City Deputy Mayor and Councillor Chris Quilkey has passed away. First and foremost, our thoughts are with Chris’s family,…

  • Unit demolished as Ipswich flood recovery continues

    Unit demolished as Ipswich flood recovery continues

    Ipswich Mayor Teresa Harding has welcomed the demolition of Mihi Grove, a flood-hit 42-unit complex in Brassall purchased as part of the Queensland and Australian Government’s Resilient Homes Fund Voluntary…

  • Fraser adopts tree

    Fraser adopts tree

    The Fraser Coast now has an official tree, with Council today adopting the Kauri Pine as a symbol of the region’s culture, history and natural environment. Fraser Coast Mayor George…