Queensland’s Boonah Shire Council has 536 kilometres of dirt roads that are used by school buses, agricultural machinery, cars and trucks. The Shire is hilly, with gradients up to 16.6 per cent and a diverse range of soil and geological formations. These factors have combined to make unsealed road maintenance a significant drain on Council’s Road Infrastructure Budget in the past. But all that has changed since Council applied a new approach to its gravel extraction and non renewable resource crushing methods.

The following is an edited extract from a paper presented by Director Works and Technical Services, Patrick Murphy, to a Leading Practice Seminar on 9 May.

The traditional approach

Traditionally, unsealed road construction and maintenance was a creeping improvement syndrome from bush tracks of poor alignment — originally meant for horse and sulkies — to a gravel standard used by modern cars as well as 42.5 tonne trucks. Many of our roads have never been constructed to meet appropriate current day standards. The delivery of the maintenance service was generally driven by a reactive need (based on complaints) rather than a planned, efficient process. Because there was no planned approach, the annual budget was based on a single historical amount plus a growth allowance. The pavement material would unravel in dry conditions and be too slippery in the wet. The higher loss of binder from traffic was accepted as standard practice. This premature failure of the pavement resulted in more frequent grading, which loosened the pavement surface, promoting the early deterioration. The demand on gravel was a major concern because of finite gravel resources and the difficulty in establishing new quarries.

The improvement process

The first and most important phase was to engage the people who actually did the work. The knowledge of staff should not be underestimated. They are the people doing the work, so they should know the real issues. Council staff were lucky to be involved with the Australian Road Research Board’s Unsealed Road Guidelines. I was invited to be a member of the technical review committee for these guidelines and Council’s key maintenance staff were trained by ARRB to use the Guidelines. The staff prepared and documented the Maintenance Management Strategy, thereby having significant ownership of the outcomes. Activity based budgeting, an inspection process and work orders were introduced. The focus of the day labour workforce changed to outcomes rather than inputs. A number of crushing contractors were used to refine Council’s gravel processing to meet ARRB specifications. The key to keeping material on the road longer is having the correct proportions of amour (rock) to binder (clay).

Positive outcomes

Improved pavement shape and material compaction have resulted in improved safety on unsealed roads, which has cut travel times and, therefore, costs. Higher quality maintenance activities are delivered for the same dollars and the annual budget is determined by road maintenance needs.

The future

We have a new operational manager who will be reviewing procedures for ongoing improvements. Investigations are being undertaken for a computer system to allow for integrated management support. At present, we have a number of home grown Access and Excel spreadsheets for monitoring and reporting. There have been innovations that are being trialed. The most notable one is the conversion of the Flocon road patrol truck to a verge spray unit, which will manage vegetation on the less busy unsealed roads.

For further information contact Patrick Murphy, email megang@boonah.qld.gov.au or telephone (07) 5463 3020.

Digital Editions


More News

  • Looking to the future

    Looking to the future

    Flinders Lane will be abuzz for two days this month with Townsville Youth Council – supported by Townsville City Council – set to deliver a free festival focused on the…

  • WA leads the way as people to the regions

    WA leads the way as people to the regions

    Ten million people now call regional Australia home, and Western Australia is leading the way with its regional population growing faster than the cities, according to a deep dive into…

  • Sewer grant sought

    Sewer grant sought

    Fraser Coast Regional Council will seek Queensland Government funding for two major water and sewerage projects with capacity to support more than 11,000 new homes across the region. At its…

  • Mayors call for waste levy

    Mayors call for waste levy

    Mayors across NSW have called for waste levy to soften the blow of fuel price increases. More than 60 Councils from across NSW have issued a call for the NSW…

  • Lismore four years on

    Lismore four years on

    Four years on: How Lismore is building back and setting a national benchmark. When the 2022 flood inundated Lismore, it was not simply another extreme weather event. It became Australia’s…

  • A golden celebration

    A golden celebration

    Cockburn Libraries will mark a major milestone in 2026 – 50 years of serving, supporting and connecting the community. Spearwood Library opened its doors on 23 March 1976 as one…

  • Local Governments vital for fuel supply

    Local Governments vital for fuel supply

    Fuel supply constraints and rising costs are putting councils and communities under increasing pressure across Australia, with implications for essential services and community infrastructure. The Australian Local Government Association is…

  • Nathan Daniell elected Mayor of Adelaide Hills Council

    Nathan Daniell elected Mayor of Adelaide Hills Council

    Adelaide Hills Council is pleased to advise that Nathan Daniell has formally been elected Mayor following confirmation of results from the supplementary election. Mr Daniell has served as a councillor…

  • Community mourns beloved former mayor

    Community mourns beloved former mayor

    The NSW local government sector is deeply saddened by the passing of former Lismore Mayor Jenny Dowell OAM, a widely respected and much-loved leader who dedicated her life to serving…

  • New-look reserve reopens

    New-look reserve reopens

    Toongabbie’s Sue Savage Reserve has reopened after a $4 million upgrade featuring a new skate park, BMX pump track, fitness equipment, an amenity building, park furniture, drainage upgrade, landscaping and…