Home » Communication a key part of building bridges

Communication a key part of building bridges

Moira Shire Council is directly responsible for the maintenance, repair and upgrade of 58 bridges on its 3,574 kilometre road network. Almost half are old timber bridges with load limits ranging from five to 15 tonne.

Most of these bridges are about 50 years old. The combined pressures of age, increasing traffic numbers, larger vehicle size, new legislative safety requirements and limited funding are likely to see increasing numbers of older bridges facing load limits or closure until Council can undertake costly repairs or replacement.

New legislative requirements of the Road Management Act associated with the removal of non-feasance mean that it is increasingly likely that local bridges may be closed or have load limits introduced at very short notice.

In May 2004, a routine inspection of Rices Bridge in Barmah revealed major structural problems requiring the immediate introduction of a five tonne load limit and repair or replacement of the bridge. The 30 metre span bridge provides the only road connection to the Barmah Forest that is suitable for large vehicles including tourist coaches, school tours, cattle trucks and fuel trucks.

Council had to act quickly to minimise inconvenience, harness community anxiety through regular communication and use the issue as an opportunity to foster and enhance relationships between Council and the Barmah community.

With the number of old and deteriorating bridges in Moira Shire, Council also took advantage of the opportunity to develop an integrated approach to bridge design and communication that could be easily and quickly transferred across the bridge network. It was also vital for Council to manage the issue in a way that would gain the trust of the community and set the standard for the future.

Moira Shire developed a solution involving all key stakeholders in decision making and developing transferable engineering techniques to maximise construction speed and quality, while minimising cost and the impact on tourism and the wider community.

The design, construction and communication techniques used for Rices Bridge maximised construction speed, minimised cost, involved key stakeholders in decisions and integrated management decisions with corporate communication objectives. The Moira community now has an integrated communication methodology, bridge design and construction techniques that can be used to minimise potential community angst arising from bridges requiring closure or load limits at short notice.

Council completed construction within 20 days, keeping the old bridge open the entire time and assisting tour operators with a shuttle bus to ferry coach passengers from the bridge to the Dharnya Aboriginal Heritage Centre and to Kingfisher Cruises on Moira Lakes.

Digital Editions


  • Mayors call for waste levy

    Mayors call for waste levy

    Mayors across NSW have called for waste levy to soften the blow of fuel price increases. More than 60 Councils from across NSW have issued…

More News

  • Community mourns beloved former mayor

    Community mourns beloved former mayor

    The NSW local government sector is deeply saddened by the passing of former Lismore Mayor Jenny Dowell OAM, a widely respected and much-loved leader who dedicated her life to serving…

  • New-look reserve reopens

    New-look reserve reopens

    Toongabbie’s Sue Savage Reserve has reopened after a $4 million upgrade featuring a new skate park, BMX pump track, fitness equipment, an amenity building, park furniture, drainage upgrade, landscaping and…

  • Temora address housing shortage in tiny hamlet

    Temora address housing shortage in tiny hamlet

    Proposed Ariah Park Village Subdivision to Address Housing Shortage – Lots from $90-000 to $110,000 in the small picturesque hamlet. Temora Shire Council is investigating the delivery of a proposed…

  • Douglas Shire seeks renewal

    Douglas Shire seeks renewal

    Creative store opens in Mossman through empty spaces program. A new store and community art space has opened in Mossman thanks to a program designed to breathe new life into…

  • New youth and community centre for McLeay

    New youth and community centre for McLeay

    A new Youth and Community Centre planned for Macleay Island will service the needs of the growing community and will also be designed so it can support community recovery following…

  • Grants close soon

    Grants close soon

    Queensland councils have until 31 March to apply for Round two of the State Government’s Secure Communities Partnership Program, which offers up to $400,000 per project for CCTV, lighting and…

  • Sod turned on major upgrade at Paul Fitzsimons Oval

    Sod turned on major upgrade at Paul Fitzsimons Oval

    Work has officially begun on the redevelopment of Paul Fitzsimons Oval with Alice Springs Town Council and the Australian Government turning the first sod this morning. Mayor Asta Hill and…

  • Lockyer send flood expert north

    Lockyer send flood expert north

    Lockyer Valley Regional Council has answered the call for assistance from a community impacted by Ex-Tropical Cyclone Koji, with a staff member from Council’s Disaster Management Unit deployed to support…

  • From books to bots

    From books to bots

    Tenterfield Library is proving that technology is more than just tools and devices. From coding and robotics to tech support, the Library has become a place where curiosity, connection and…

  • Major repairs for levee

    Major repairs for levee

    Goondiwindi Regional Council has endorsed its largest-ever capital works project to repair and reinforce critical sections of the Goondiwindi levee, following significant erosion after recent floods. At this week’s Ordinary…