Byron pushes for drainage upgrade following floods

Byron Council is investigating the flooding event in the Byron Bay town centre and Suffolk Park, 30 March 2022, which saw many homes and businesses inundated with water.

The Bureau of Meteorology gauges recorded 319mm of rain at Coopers Shoot and 282mm in Byron Bay in the 24 hours to 9am on 30 March.

That amount of rain alone would ordinarily have caused flooding in Byron Bay, but the already soaked catchment is believed to have exacerbated the problem with no water being absorbed into the ground.

The intensity of the rain was beyond the capacity of Council’s drainage pipe network.

In addition to this, the level of the ocean is currently higher than normal due to spring tides,so water flowing out of Belongil Creek and Tallow Creek was slowed considerably when the ocean was pushing against it.

Phil Holloway, Infrastructure Services Director, said it was terrible to see the flooding of homes and businesses in Byron Bay and Suffolk Park.

“It’s incredibly sad to see this flood event on top of everything else we’ve experienced, not only in the last month, but during the pandemic as well,” Mr Holloway said.

“The town of Byron Bay is actually very flood-prone when we get heavy rain,” he said.

“As soon as we could we started checking the drains for blockages.

“The Clarks Beach drain was blocked and we did clear that yesterday afternoon and that helped some of the water get away.

“Normally that drain, which silts up with sand, clears itself when there is heavy rain but that didn’t happen this time.

“We didn’t find any other major blockages in the network,” Mr Holloway said.

It’s estimated a drainage upgrade in Byron Bay will cost around $15 million and Council has applied for funding for this project, but so far has been unsuccessful, in getting Government grants to enable this work to get started.

“This drainage upgrade is a top priority for us but the cost is beyond the capacity of Council,” Mr Holloway said.

“Flooding in any business or household is not something we want to see and we will continue to apply for grants for this important project,” he said.

Digital Editions


  • Lockyer send flood expert north

    Lockyer send flood expert north

    Lockyer Valley Regional Council has answered the call for assistance from a community impacted by Ex-Tropical Cyclone Koji, with a staff member from Council’s Disaster…

More News

  • Lockyer announce Scott Greensill as CEO

    Lockyer announce Scott Greensill as CEO

    Lockyer Valley Regional Council has appointed Scott Greensill as its new Chief Executive Officer. Councillors formally approved the appointment of Mr Greensill at a Special Meeting of Council in February.…

  • Myers resigns for health reasons

    Myers resigns for health reasons

    Wollongong’s Councillor Tiana Myers has resigned, as a Ward Three Councillor for City Council due to health reasons. Cr Myers was elected to Council in 2024 with a focus on…

  • Acknowledging women’s role in councils

    Acknowledging women’s role in councils

    Council representatives from across the state gathered in Sydney today for Local Government NSW’s (LGNSW) International Women’s Day event. Mayor Darcy Byrne, President of LGNSW, said the event was an…

  • Kylie Davies beats strong field

    Kylie Davies beats strong field

    Flinders Shire Council is pleased to announce the appointment of Kylie Davies as its new Chief Executive Officer. Ms Davies will start in the role on 13 April following a…

  • Leaving on a high

    Leaving on a high

    Mount Alexander Shire Council’s Chief Executive Officer Darren Fuzzard will end his tenure at the council in July 2026, marking ten years of service to the organisation and community. Mr…

  • Safety first for transport corridor

    Safety first for transport corridor

    Traversing a major Townsville transit corridor spanning three suburbs will soon be safer for motorists, cyclists and pedestrians, with Townsville City Council commencing a $3.8 million upgrade of Hugh and…

  • Creating long-term employment pathways

    Creating long-term employment pathways

    The Shire of Carnarvon is creating long-term employment pathways and strengthening workforce capability through its participation in the Remote Jobs and Economic Development (RJED) Program, a national initiative designed to…

  • Cool summer plan for Campbelltown

    Cool summer plan for Campbelltown

    Extreme heat is the biggest killer of natural disasters in Australia, exceeding that for any other environmental disaster combined, including floods, storms, bushfires and cyclones. While high temperatures pose risks…

  • Bathurst has it’s scrap together

    Bathurst has it’s scrap together

    Bathurst Regional Council has successfully concluded its ‘Let’s Get Our Scrap Together’ campaign, launched on 1 September 2025 with funding from the NSW Government and delivered in collaboration with NetWaste…

  • Baw Baw acting CEO tenure extended

    Baw Baw acting CEO tenure extended

    Baw Baw Shire Council has extended the contract of Acting Chief Executive Officer Sally Jones until 30 June 2026. The matter was considered as a confidential item in the late…